GROUNDFORCE DEVELOPS UNIQUE SOLUTION FOR EXCAVATION AT LIMERICK HOSPITAL

Groundforce equipment has played a crucial role in the construction of a new extension to University Hospital, Limerick, in Ireland.

The new 9,800m2 acute ward, is built over the existing emergency department and dialysis unit and consists of 96 ensuite single rooms over four floors.

As part of the project, main contractor Sisk was required to build a new lift core, adjoining the existing hospital building and lower-level car park, to service the new structure.

The lift core rises from an 8m-deep excavation dug immediately adjacent to the existing building. The bottom 4m of this excavation was in the bedrock, comprising a hard granite material, and was self-supporting. The upper 4m was in the overlying soil and required temporary support to prevent any collapse.

This was the element of the project that required the services of Groundforce.

“The excavation needed temporary support on three sides – the fourth side was the wall of the existing hospital building,” explains Groundforce director Joseph Lenihan.

The usual method employed by Groundforce is to support the sheet-piled retaining walls with modular extendable waling beams around the perimeter and hydraulic props spanning the excavation from side to side and bearing on the waling beams.

However, the size of this excavation (measuring approximately 14m x 17.5m) and its location against the wall of an existing building required a different approach.

“It was acceptable to the client for the adjoining wall to take a shear load from the shoring system but not a point load,” says Joseph Lenihan, “Therefore the shoring system had to rely on lateral restraint from the adjacent ground.”

The shoring system comprised two levels of Mega Brace frame supporting the 5m-long Larssen L603 sheet piles lining the excavation and four of Groundforce’s MP150 modular hydraulic props installed as corner struts at the end of the excavation furthest from the hospital building.

Groundforce also supplied the MS4 piling hammer to install the sheet-piles. Perimeter safety was provided in the form of Groundforce’s Edgesafe barrier and davit-arm rescue system.

The lateral loads from the three braced sides of the excavation were transferred along the line of the sheet-piled retaining walls which, together with the earth behind them, provided a shear key to prevent any point load transferring to the adjacent building.

The shoring system design was developed jointly by Groundforce and Sisk’s temporary works department and approved by the project’s consulting engineer, Arup.

“During the design stage a concern was raised by the Sisk design team regarding the transfer of the load to the shear key,” says Joseph Lenihan. “A typical hydraulic bracing system is pressurised to prevent any lateral movement. However, this lack of movement would not allow the shear key to take effect – the adjacent ground would not be given the chance to take the load.

“The solution was to not lock-off the ram element of the frame, thereby allowing it to contract once the system became loaded. This allowed a certain amount of movement and ensured that no point load was transferred to the adjacent wall.

“It’s fair to say that we’ve never done this before,” he adds.

The unique requirements of this operation demanded close collaboration between designers from Groundforce and Sisk’s temporary works department.

“There was a lot of design development required, not just for the shoring system itself but for the sequence of its installation and removal,” says Sisk’s project manager Stephen Geraghty.

“In fact, almost as much design went into the removal of the temporary works as for the installation. The sequence of backfilling to a certain level, concreting and removing the bracing had to be carefully planned,” he adds.

Carrying out the work so close to the existing building brought the added risk of disturbance to the hospital’s staff and patients. Noise and vibration therefore had to be kept to the absolute minimum and was carefully monitored.

“When it came to excavating through the rock we had to bring in a specialist to drill it out in small sections instead of going in there with heavy machinery. The excavation was quite slow: the first two or three weeks were spent just drilling/hydraulic breaking rock,” says Stephen Geraghty.

During the works, weekly design workshops ensured that the temporary works element remained under scrutiny.

“It was certainly tricky. But we kept in constant dialogue with Groundforce and I can’t complement them enough,” he adds.

 _____________________________________________________

Michael McDonnell Managing Editor of Irish Construction Industry Magazine & Plan Magazine

Email: michael@irishconstruction.com      WWW.MCDMEDIA.IE 

 

Continue Reading

  • |

    Purcell Construction appointed to €173m Parnell Square Cultural Quarter project

    Purcell Construction appointed to €173m Parnell Square Cultural Quarter project Dublin City Council has appointed Purcell Construction Limited as main contractor for Phase 1 of the Parnell Square Cultural Quarter – New City Library project, with construction due to commence in the coming weeks. With an estimated all-in project cost of €173.2 million, the development…

  • |

    Why Integrated heating Design is Becoming Critical for new Homes

    Why Integrated Heating Design is Becoming Critical for New Homes As Ireland’s residential construction sector continues to deliver homes to increasingly demanding energy performance standards, heating system design can no longer be treated as a standalone element of a project. Instead, it is becoming an integral part of the overall building design process, influencing everything…

  • Sisk Group reports 27.7% increase in profit before tax to €74.2m

    Sisk Group reports 27.7% increase in profit before tax to €74.2m Sicon Limited, the parent company of John Sisk & Son’s construction and related businesses in Ireland, the UK and Europe, has reported a strong financial performance for the year ended 31 December 2025, with profit before tax increasing by 27.7% to €74.2m. Operating profit…

  • Engineering shortage threatens housing and infrastructure delivery, Engineers Ireland warns

    Engineering shortage threatens housing and infrastructure delivery, Engineers Ireland warns A shortage of engineers and delays in delivering critical infrastructure are putting Ireland’s housing targets, transition to low-carbon energy and economic competitiveness at risk, Engineers Ireland has warned. In its Pre-Budget 2027 Submission, the professional body, which represents more than 30,000 members, warns that Ireland…

  • |

    New R290 Heat Pump from Pipelife

    New R290 Heat Pump from Pipelife Pipelife launches indoor R290 heat pump designed for Irish apartments Pipelife Ireland has launched a new indoor monoblock heat pump designed specifically for the demands of Irish apartment construction. The system has been developed from the ground up and rigorously tested to reflect real-world building conditions, rather than relying…