GROUNDFORCE DEVELOPS UNIQUE SOLUTION FOR EXCAVATION AT LIMERICK HOSPITAL

Groundforce equipment has played a crucial role in the construction of a new extension to University Hospital, Limerick, in Ireland.

The new 9,800m2 acute ward, is built over the existing emergency department and dialysis unit and consists of 96 ensuite single rooms over four floors.

As part of the project, main contractor Sisk was required to build a new lift core, adjoining the existing hospital building and lower-level car park, to service the new structure.

The lift core rises from an 8m-deep excavation dug immediately adjacent to the existing building. The bottom 4m of this excavation was in the bedrock, comprising a hard granite material, and was self-supporting. The upper 4m was in the overlying soil and required temporary support to prevent any collapse.

This was the element of the project that required the services of Groundforce.

“The excavation needed temporary support on three sides – the fourth side was the wall of the existing hospital building,” explains Groundforce director Joseph Lenihan.

The usual method employed by Groundforce is to support the sheet-piled retaining walls with modular extendable waling beams around the perimeter and hydraulic props spanning the excavation from side to side and bearing on the waling beams.

However, the size of this excavation (measuring approximately 14m x 17.5m) and its location against the wall of an existing building required a different approach.

“It was acceptable to the client for the adjoining wall to take a shear load from the shoring system but not a point load,” says Joseph Lenihan, “Therefore the shoring system had to rely on lateral restraint from the adjacent ground.”

The shoring system comprised two levels of Mega Brace frame supporting the 5m-long Larssen L603 sheet piles lining the excavation and four of Groundforce’s MP150 modular hydraulic props installed as corner struts at the end of the excavation furthest from the hospital building.

Groundforce also supplied the MS4 piling hammer to install the sheet-piles. Perimeter safety was provided in the form of Groundforce’s Edgesafe barrier and davit-arm rescue system.

The lateral loads from the three braced sides of the excavation were transferred along the line of the sheet-piled retaining walls which, together with the earth behind them, provided a shear key to prevent any point load transferring to the adjacent building.

The shoring system design was developed jointly by Groundforce and Sisk’s temporary works department and approved by the project’s consulting engineer, Arup.

“During the design stage a concern was raised by the Sisk design team regarding the transfer of the load to the shear key,” says Joseph Lenihan. “A typical hydraulic bracing system is pressurised to prevent any lateral movement. However, this lack of movement would not allow the shear key to take effect – the adjacent ground would not be given the chance to take the load.

“The solution was to not lock-off the ram element of the frame, thereby allowing it to contract once the system became loaded. This allowed a certain amount of movement and ensured that no point load was transferred to the adjacent wall.

“It’s fair to say that we’ve never done this before,” he adds.

The unique requirements of this operation demanded close collaboration between designers from Groundforce and Sisk’s temporary works department.

“There was a lot of design development required, not just for the shoring system itself but for the sequence of its installation and removal,” says Sisk’s project manager Stephen Geraghty.

“In fact, almost as much design went into the removal of the temporary works as for the installation. The sequence of backfilling to a certain level, concreting and removing the bracing had to be carefully planned,” he adds.

Carrying out the work so close to the existing building brought the added risk of disturbance to the hospital’s staff and patients. Noise and vibration therefore had to be kept to the absolute minimum and was carefully monitored.

“When it came to excavating through the rock we had to bring in a specialist to drill it out in small sections instead of going in there with heavy machinery. The excavation was quite slow: the first two or three weeks were spent just drilling/hydraulic breaking rock,” says Stephen Geraghty.

During the works, weekly design workshops ensured that the temporary works element remained under scrutiny.

“It was certainly tricky. But we kept in constant dialogue with Groundforce and I can’t complement them enough,” he adds.

 _____________________________________________________

Michael McDonnell Managing Editor of Irish Construction Industry Magazine & Plan Magazine

Email: michael@irishconstruction.com      WWW.MCDMEDIA.IE 

 

Continue Reading

  • |

    Chryso and Ecocem Combine Expertise to Accelerate Low-Carbon Concrete Development

    Chryso and Ecocem are combining their expertise in cement technology and construction chemistry to accelerate the development and adoption of high-performance, low-carbon concrete. Unveiled at BATIMAT 2026, the new solution combines Ecocem ACT low-carbon cement technology with EnviroMix® 3150 ACT, a new admixture solution developed jointly by Chryso and Ecocem. The collaboration is designed to…

  • |

    BUILD FASTER, BUILD BETTER, BUILD FOR IRELAND’S FUTURE WITH IZODOM ICF

    As the Irish construction sector evolves to meet stringent NZEB and sustainability requirements, choosing the right Insulated Concrete Formwork (ICF) system is more critical than ever. While the Irish market is familiar with several established ICF brands, one manufacturer stands apart in delivering a complete, certified Passive House building envelope directly to your site: IZODOM….

  • ACEI HOSTING NETWORKING EVENT

    The ACEI is hosting an informal but purposeful event to celebrate equality, diversity and inclusion in the engineering sector on October 10 between: 4:00pm – 7:00pm at The Leinster, Mount Street Lower, Dublin 2, D02 WK33. The networking event will be hosted by ACEI President Anne-Marie Conibear and feature speakers from Nicholas O’Dwyer Consulting Engineers…

  • LAND DEVELOPMENT AGENCY WELCOMES GOVERNMENT FUNDING ANNOUNCEMENT

    The Land Development Agency (LDA) has welcomed the Government’s announcement that it will receive a further €1.25 billion in equity capital. This further capitalisation will enable the Agency to continue to its mission of delivering affordable homes across Ireland and assist in meeting the country’s housing need. This additional capital will facilitate further new affordable…

  • DEPARTMENT OF HOUSING, LOCAL GOVERNMENT AND HERITAGE BUDGET PACKAGE OF ALMOST €8BN ANNOUNCED

    Record capital €6bn funding for housing€2.7bn package for Uisce Éireann to deliver necessary water infrastructure & support housingSignificant funding for Local Authorities, Planning and Heritage The Government’s commitment to Housing, Local Government and Heritage was emphasised in an overall budget package of €7.93bn announced today by Minister for Housing, Local Government and Heritage, Darragh O’Brien…

  • SISK SET TO PIONEER A WORLD FIRST LOW CARBON CONCRETE TECHNOLOGY

    Sisk-led consortium secures £500,000 fund from Innovate UK Sisk in collaboration with a consortium of leading low carbon industry experts has announced that it has been successful in securing £500,000 from Innovate UK funding as part of the Contracts for Innovation: Decarbonising concrete competition, to invest in a pioneering scalable low carbon demonstrator, marking a…