HOLLYWOODRATH SCHOOL
|

HOLLYWOODRATH SCHOOL

HOLLYWOODRATH SCHOOL

As part of the Department of Education’s enhanced modular buildings programme, Actavo Modular was selected to provide a state-of-the-art two-storey building to Hollywoodrath School in Hollystown, Dublin 15, covering 4,223sqm. The project was completed in only 14 months.

Scope of works
Actavo Modular created a bespoke design to meet the school’s requirements. It comprises of 24 classrooms, a two-classroom special education needs unit and external facilities. Material quantities included:

• 150mm concrete composite floor (cast off site in manufacturing facility in Kill and transported and installed on site).
• 750m2 of brick slip
• 375m2 of render
• 1,200m2 of curtain walling
• 4,850m2 of external paving
• 4,500m2 of roadways and car park area
• 20,000m3 of reduced level dig
• 1,400m3 of raft slab

Services delivered
• A comprehensive turnkey service that includes design, fabrication, installation and delivery of 152 steel framed modular sections, comprising 4,223sqm in total and incorporating a feature staircase. The heaviest module weighed over 36 tons.

• All civils works were carried out, including external hard and soft play areas, two ballcourts, car parking and bus set down areas.

Key successes
• As the largest enhanced modular buildings project in Ireland to date, this project marks a pivotal moment in the modular construction industry.
• Combination of permanent and modular building solutions with the use of concrete flooring.
• High safety compliance on site with zero LTIs for the full duration of the project.

Community engagement
Throughout the duration of the project, we remained consistently attentive to the needs and concerns of the surrounding community. There was proactive engagement with the Neighborhood Watch group and a system was established to promptly address any concerns. Controlling noise pollution was prioritised to ensure minimal disruption to local residents.

Solutions to challenges
• Bringing in 152 modules without disrupting traffic or surrounding neighbourhoods was a challenge. Actavo Modular worked in conjunction with our transport partners and neighbouring communities to safely deliver the 4m wide modules.
• Challenging ground conditions on site required extensive civils works to be completed prior to module delivery to site.
• Significant planning and care went into the logistics of lifting such extreme loads in the manufacturing facility and their installation on site. Complex lifting plans were put in place to assess the weight of each individual module and to strategically place temporary supports and lifting points to each module. This ensured modules ascended and descended vertically and level into position.

Benefits to client
• In excess of 80% of the building fit-out was completed in our factory pre-delivery, saving the client time and money.
• The building’s standard 60 year structural warranty will serve the local community for generations.
• Using innovative materials, the school is designed to achieve optimum energy efficiency, flexible interconnectivity and structural integrity.

actavo.com/school-project

______________________________________________________________________________________

Michael McDonnell Managing Editor of Irish Construction Industry Magazine & Plan Magazine

Email: michael@irishconstruction.com      WWW.MCDMEDIA.IE 

 

Continue Reading

  • |

    GROWTH, INNOVATION AND SUSTAINABILITY IN IRELAND’S CONSTRUCTION INDUSTRY

    Ireland’s construction sector is poised to deliver a model of sustainable construction excellence for the decade ahead – if it can adapt, writes Colm McGrath The Irish construction industry in 2025 stands at a decisive turning point. Sustained Government investment, rapid urbanisation and the drive for sustainability are propelling growth across housing, infrastructure and commercial…

  • ABOLISH THE RED TAPE

    Ken MacDonald, Managing Director at Hooke & MacDonald, talks about the new guidelines around apartment building, the obstacles to housing delivery and why bureaucracy is prolonging the housing crisis Established in 1967 by Ken MacDonald, Hooke & MacDonald is one of the longest established and best-known estate agents in Ireland. Ken is synonymous with the…

  • THE VALUE OF EARLY COLLABORATION

    Timing can make or break a construction project – and nowhere is this more evident than in the planning and integration of temporary works. Despite their critical role, temporary works can still often be an afterthought, introduced well after key design decisions have already been made. Here, Wayne Fisher, International Business Development Director at MH…

  • MMC: THE FASTEST ROUTE TO INCREASING HOUSING DELIVERY IN IRELAND

    Paul Tierney, Chief Executive Officer at MMC Ireland, talks about what we must address to unlock the potential of MMC Ireland’s housing crisis is now widely accepted as one of the most urgent and complex challenges facing the country. Despite well-intentioned strategies and increased public investment, delivery continues to lag behind demand. In this context,…

  • |

    TACKLING IRELAND’S VACANCY CRISIS

    Cross-sector coalition calls for stronger action on vacancy and dereliction to deliver more housing Dedicated vacancy teams in local authorities, expanded reuse grants and a wider suite of tax measures are required to tackle Ireland’s vacancy crisis and deliver much needed homes, according to recommendations launched by the Vacant to Vibrant Building Alliance (VVBA), a…

  • SISK SIGNS UP FOR €21M ROYAL REDEVELOPMENT

    Páirc Tailteann Stand construction marks major milestone for Meath Sisk and Meath GAA have announced that a €21M contract has been signed for the redevelopment of the stand at Páirc Tailteann. This signing represents an important milestone in delivering enhanced facilities for players, members, supporters, and the wider community. The agreement was formalised on Saturday,…