GROUNDFORCE RISES TO RIVERSIDE CHALLENGE

GROUNDFORCE RISES TO RIVERSIDE CHALLENGE

Groundforce has supplied its KD6 steel sheet piles and modular hydraulic Mega Brace frames to support a deep excavation for housebuilders Ballymore who are building a large mixed-tenure housing development at the village of Ballymore Eustace, County Kildare, on the banks of the River Liffey. Called River Walk, the project comprises a variety of two, three and four-bed houses plus local amenities, laid out in landscaped grounds between the river and the existing village.

Groundforce

One essential part of the development’s infrastructure is the drainage system, comprising a storage tank and sump to collect foul water and pump it up into the main sewer. Comprising two precast concrete units, this system was installed in two deep back-to-back excavations measuring 13m in length and 8m wide.

“The ground conditions were very challenging,” says Colin Comerford, site foreman for Tower Civil Engineering, which has the contract for all the groundworks and drainage on the project.

“The excavation was only about 30m from the river, so the water table was very high. Plus, the ground is very loose and sandy down to 3m and mostly just gravel below that,” he explains.

Structural support was therefore crucial in the installation of the two concrete tanks and Tower Civil Engineering turned to Groundforce for a solution. A steel sheet-piled cofferdam was essential to hold back the loose ground but the side-to-side bracing usually employed to withstand the high ground pressures was not an option because the excavation had to be completely clear to allow the two large precast tanks to be lifted in.

Groundforce therefore chose to install its hydraulic Mega Brace frame at three levels around the perimeter of the excavation to support the sheet piles.

“The biggest challenge for us was the fact that the two excavations were at different formation levels – 5.81m and 4.75m – so we had to design the Mega Brace frames to suit both levels,” says Groundforce area manager Jason Hunter.

That required a staggered cofferdam using KD6 steel sheets in lengths of 5m and 7m.

“The frames also had to be staggered to get the right levels and avoid clashing with the pipes that run through both tanks,” explains Jason.

The gravelly ground and high water table meant problems with flooding in the excavation, which once complete, required construction of an insitu concrete base. To manage this, Tower Civil Engineering had two dewatering pumps – one 6” and one 4” – running constantly.

The excavation was completed early this summer and the two tanks installed by crane with no difficulty.

“We’re very, very happy with the solution provided by Groundforce,” says Colin. “It all went without a hitch but Jason was always available if we needed help or advice.”

 ______________________________________________________

Denise Maguire   Editor of Irish Construction Industry Magazine & Plan Magazine

Email: denise@mcdmedia.ie      WWW.MCDMEDIA.IE  WWW.IRISHCONSTRUCTION.COM

Continue Reading

  • |

    Chryso and Ecocem Combine Expertise to Accelerate Low-Carbon Concrete Development

    Chryso and Ecocem are combining their expertise in cement technology and construction chemistry to accelerate the development and adoption of high-performance, low-carbon concrete. Unveiled at BATIMAT 2026, the new solution combines Ecocem ACT low-carbon cement technology with EnviroMix® 3150 ACT, a new admixture solution developed jointly by Chryso and Ecocem. The collaboration is designed to…

  • |

    BUILD FASTER, BUILD BETTER, BUILD FOR IRELAND’S FUTURE WITH IZODOM ICF

    As the Irish construction sector evolves to meet stringent NZEB and sustainability requirements, choosing the right Insulated Concrete Formwork (ICF) system is more critical than ever. While the Irish market is familiar with several established ICF brands, one manufacturer stands apart in delivering a complete, certified Passive House building envelope directly to your site: IZODOM….

  • ACEI HOSTING NETWORKING EVENT

    The ACEI is hosting an informal but purposeful event to celebrate equality, diversity and inclusion in the engineering sector on October 10 between: 4:00pm – 7:00pm at The Leinster, Mount Street Lower, Dublin 2, D02 WK33. The networking event will be hosted by ACEI President Anne-Marie Conibear and feature speakers from Nicholas O’Dwyer Consulting Engineers…

  • LAND DEVELOPMENT AGENCY WELCOMES GOVERNMENT FUNDING ANNOUNCEMENT

    The Land Development Agency (LDA) has welcomed the Government’s announcement that it will receive a further €1.25 billion in equity capital. This further capitalisation will enable the Agency to continue to its mission of delivering affordable homes across Ireland and assist in meeting the country’s housing need. This additional capital will facilitate further new affordable…

  • DEPARTMENT OF HOUSING, LOCAL GOVERNMENT AND HERITAGE BUDGET PACKAGE OF ALMOST €8BN ANNOUNCED

    Record capital €6bn funding for housing€2.7bn package for Uisce Éireann to deliver necessary water infrastructure & support housingSignificant funding for Local Authorities, Planning and Heritage The Government’s commitment to Housing, Local Government and Heritage was emphasised in an overall budget package of €7.93bn announced today by Minister for Housing, Local Government and Heritage, Darragh O’Brien…

  • SISK SET TO PIONEER A WORLD FIRST LOW CARBON CONCRETE TECHNOLOGY

    Sisk-led consortium secures £500,000 fund from Innovate UK Sisk in collaboration with a consortium of leading low carbon industry experts has announced that it has been successful in securing £500,000 from Innovate UK funding as part of the Contracts for Innovation: Decarbonising concrete competition, to invest in a pioneering scalable low carbon demonstrator, marking a…