FIXED PRICE CONTRACTS: A MYTHICAL CREATURE?

Shane Dolan and Stephen McGonagle outline the options open to contractors struggling to achieve fixed price contracts

With construction cost inflation soaring in recent times, builders and developers are facing significant challenges to achieve fixed price contracts that were routinely agreed in the market until very recently. Market factors have significantly changed the dynamic in the past two years and more acutely since February 2022. Many contractors are simply refusing to execute fixed price contracts.

FIXED PRICE
Shane Dolan, Partner, Mason, Hayes & Curran

The primary drivers of the cost increases are Brexit, the war in Ukraine, Covid-related delays, increasing energy costs and general economic inflation. The price for structural steel, for example, has reportedly increased by approximately 140% between September 2020 and August 2022. Employers, contractors, funders, investors and their advisors are increasingly utilising innovative solutions to address their respective concerns. A variety of approaches and solutions may be considered, depending on the context and the parties’ sensitivity to cost risk.

FIXED PRICE, SUBJECT TO CARVE OUTS
The parties can agree a fixed price subject to adjustments being allowed for (i) certain risks occurring; or (ii) costs increasing in certain respects, particularly where those are not within the control of the contractor or capable of being mitigated. The key consideration is to understand the parameters around the entitlement. Purely by way of example:

Contingency/capped adjustments/risk sharing
The parties may agree a fixed price subject to the parties accepting that the cost consequences for a specific risk are either shared or taken by one party, up to a particular value or within specified thresholds.

MITIGATION MEASURES AGREED AROUND KEY RISKS
The parties can agree a fixed price on the basis that specified procedures or protocols are in place to mitigate the cost impact. For example:

Pre-ordering materials that are subject to regular anticipated inflation Where the design is complete and quantities of materials are known, the contractor may pre-order the relevant materials to lock in the current price for that package, such as rebar. This solution may require upfront payment, additional storage and security costs, advance payment bonds and vesting certificates where the materials are held off-site. The terms of the contract would need to facilitate each of these.

Early warning mechanisms
The parties can agree that the contractor will produce a procurement risk schedule and agree to engage at regular intervals with suppliers to ensure that any delays or additional costs are flagged as early as possible in the project. In specified circumstances, subject to the contractor complying with the protocol, the employer may accept an element of additional cost.

PUBLIC WORKS CONTRACT INFLATION CO-OPERATION FRAMEWORK
In May 2022, the Government introduced a framework to apportion inflation costs in the public works suite of contracts. Under the framework, the employer may assume a share of up to 70% of inflation costs on the basis of an ex-gratia payment. However, the application of the framework is limited to the projects that are subject to the public work forms of contract. Further, it is not mandatory and only covers costs incurred after 1 January 2022.

GOING FORWARD
The forms of fixed price building contracts and development agreements that were routinely seen up to recent years are now a rarity, due in large part to hyper-inflation experienced across a broad range of materials. As a result, contractors are taking a more considered approach to pricing terms and it is having a material effect on the time it is taking to get contracts over the line and signed.

Parties are increasingly seeking to address the issue of rising costs in a nuanced and innovative way. The commercial discussions and drafting we are seeing in contracts reflects the complexity of the challenge.

This article was written by Shane Dolan, Partner and Stephen McGonagle, Associate, Mason, Hayes & Curran

 _____________________________________________________

Denise Maguire   Editor of Irish Construction Industry Magazine & Plan Magazine

Email: denise@mcdmedia.ie      WWW.MCDMEDIA.IE  WWW.IRISHCONSTRUCTION.COM

 

Continue Reading

  • KILSARAN RECRUITING FOR NEW PRECAST PLANT

    KILSARAN RECRUITING FOR NEW PRECAST PLANT Kilsaran is excited to announce its entry into the precast market with the launch of a new precast concrete manufacturing facility at our Brownstown site in County Kildare. This site scheduled to come on stream in early 2021 will be dedicated to the delivery of factory finished materials to…

  • CIF PARTNERS WITH LIGHTHOUSE CONSTRUCTION INDUSTRY CHARITY

    CIF PARTNERS WITH LIGHTHOUSE CONSTRUCTION INDUSTRY CHARITY The CIF is partnering with the Lighthouse Construction Industry Charity to promote better mental health and wellbeing within the Irish construction industry. The charity launched their 24/7 Construction Industry Helpline and app in Ireland in June and are the only charity providing free and confidential financial, physical and…

  • CLEVERNET – NEW START-UP – IMPROVED ENERGY EFFICIENCY

    CLEVERNET – NEW START-UP – IMPROVED ENERGY EFFICIENCY CLEVERNET, a recently established Irish start-up, is targeting the owners and managers of commercial buildings with a suite of innovative intelligent services that will enable the management of their premises more efficiently. CLEVERNET’s service is based on the deployment of wireless technology and AI over a unique…

  • ATKINS-DESIGNED RYANAIR OFFICE CAMPUS, AIRSIDE GREEN, COMPLETED

    ATKINS-DESIGNED RYANAIR OFFICE CAMPUS, AIRSIDE GREEN, COMPLETED Ryanair’s new 10,700m2 six-storey office campus, Airside Green, has officially been completed. The development, which sits alongside Ryanair’s existing head office at Airside Business Park near Dublin Airport, was designed by Atkins, a member of the SNC-Lavalin Group. The office development is part of Ryanair’s new generation of…

  • SISK AWARDED DUNKETTLE INTERCHANGE UPGRADE SCHEME

    SISK AWARDED DUNKETTLE INTERCHANGE UPGRADE SCHEME Investment of €215 million in total and is anticipated to be completed by Q1 2024. John Sisk & Son has been awarded the contract for the Dunkettle Interchange Upgrade Scheme following Tuesday’s cabinet meeting. The project includes changes to the N8, the N25 and the N40 and links to…

  • NEOLITH EASTERN PROMISE

    NEOLITH® – EASTERN PROMISE Neolith® universally specified across special Shenzhen Showroom China is becoming one of the most exciting construction markets in the world. It’s a nation with a young, vibrant and creative design community, recently come of age and producing highly original and ambitious architecture. Fast-paced and dynamic, aesthetic trends emerge on a daily…